State of the Environment Reporting on the Internet
Critical resources
Hardware
Software
External expertise
Task
. . .
. . .
Data collection Data preparation Writing and editing Graphical design HTML programming CD-ROM
. . . .
Human resources are the most expensive and critical ones. Carefully plan the allocation of your staff time following a project plan.
Generic SoE project plan
Plan/table of contents Terms of reference Start-up meeting
Data collection Data processing
Writing and editing Intermediate review Graphical production HTML programming Final review CD-ROM Launch of the SoE Evaluation and updating
The overall project duration may vary from months to years, depending upon the scope of the report
your kitchen 0
6
Cookbook for SoE Reporting
Made with FlippingBook - Online magazine maker